Greenfield House Masonry Tops Out

After months of diligent effort, the masonry work at the Greenfield House is reaching its final stages, with lintels and beams cast. The construction of exterior walls and interior partitions commenced in early August, once the on-grade slab had cured fully. Next on the schedule is the initiation of roof framing, marking another significant milestone in this project's development. Keep an eye out for more detailed progress updates soon.